Construction History

Sta 88
stumps
The lot before clearing.
graded1
The lot after clearing and grading.
graded2
The graded lot ready for construction to begin by Asheboro Construction.
pad
The concrete pad poured and ready for the building.
build1
4/11/13
build2
4/22/13
interior
4/22/13 - Starting to work on the interior.
complete
8/1/13 - Complete and in service.